Free Contractor Tool
Schedule of Values Calculator
Build a line-item schedule of values the way a G703 continuation sheet works, and get the G702 summary out the other end — completed and stored, retainage withheld, and the current payment due on this application.
Built by SubcontractorHub — the software contractors use to quote, finance, and run every job.
Book a Demo
Build Your Schedule of Values
Edit the line items below, or add your own. Enter the cumulative percentage complete for this application and the percentage certified on the previous one — the difference is what you are billing this period.
1. Schedule of values (G703 line items)
| Description of work | Scheduled value | % prev. | % complete | Stored materials | Completed + stored | Balance to finish | |
|---|---|---|---|---|---|---|---|
| $45,000.00 | $0.00 | ||||||
| $28,000.00 | $0.00 | ||||||
| $151,500.00 | $33,500.00 | ||||||
| $68,160.00 | $73,840.00 | ||||||
| $14,400.00 | $81,600.00 | ||||||
| $0.00 | $34,000.00 | ||||||
| Totals | $530,000.00 | 57.9% | $22,000.00 | $307,060.00 | $222,940.00 |
2. Retainage terms
Typically 5–10%.
Contract-specific. Check yours.
3. G702 payment summary
Contract sum
$530,000.00
Sum of all scheduled values
Total completed & stored
$307,060.00
57.9% of contract
Work completed this period
$102,560.00
Cumulative less previous
Retainage @ 10%
$30,706.00
On work + stored
Total earned less retainage
$276,354.00
Less previous certificates
$164,250.00
Current payment due
$112,104.00
This models a standard AIA-style G702/G703 application: cumulative percentage complete per line, plus stored materials, less retainage, less previous certificates. It assumes a single flat retainage rate with no step-down, treats previous certificates as prior work net of the same rate, and does not model change-order lines, contract-value retainage caps, retainage already released, stored-material documentation requirements, or sales tax. All calculations are estimates based on historical information and should be verified by the user. This tool is provided as a free service for planning purposes only and is not a substitute for professional accounting, financial, or legal advice.
From Material Takeoffs to a Signed Proposal
SubcontractorHub is the platform contractors use to turn takeoffs like these into a branded proposal, financing the customer can accept on the spot, and a scheduled job — without re-entering the job anywhere. This tool is free to use; the platform is here if you want a closer look.
The schedule of values is where commercial work stops resembling residential work. A residential replacement is quoted, signed, installed, and invoiced. A commercial job is billed in draws against an approved line-item baseline, with a percentage argued each month and a slice withheld until closeout. If the accepted proposal does not carry forward into that baseline, somebody rebuilds it by hand every month — which is where billing errors and payment delays come from. See how proposals flow into project management on one job record.
How a Pay Application Adds Up
(Work completed to date + stored materials) − retainage − previous certificates = payment due
Retainage comes off the cumulative earned amount, not off this period's work alone.
Line items should be verifiable, not just numerous
The purpose of the SOV is to make percentage complete an observation rather than an opinion. Break the work the way it actually gets installed — by system, phase, floor, or area — so someone can walk the job and confirm the number. A single large lump line invites a monthly argument about whether it is 40% or 60% done, and that argument is what delays payment. Too many lines is the opposite failure: every application becomes an accounting exercise and small errors compound.
Front-loading is the mistake owners look for
Loading value into mobilization and submittals gets cash in early, and owners and construction lenders review for it specifically. Both outcomes are bad: the SOV is rejected and your first application is delayed by a revision cycle, or it is approved and you spend the back half of the job doing work you have already been paid for with nothing left to finish it. Watch the balance-to-finish column — that is the one that gives it away.
Change orders need their own lines
Once the SOV is approved it is the billing baseline, and value cannot be shuffled between lines without consent. Approved change orders are the legitimate way to change it — they add lines and adjust the contract sum. This is why unprocessed change orders hurt so much: the work is finished but there is no approved line to bill it against, so it sits unbilled while you carry the cost. Price the impact with the change order calculator and model the withholding with the retainage calculator.
Stored materials are conditional money
Billing for equipment sitting on site is legitimate on most commercial contracts, but it is usually conditioned: materials on site rather than at the supplier, insured, and supported by paid invoices or bills of sale. Some contracts withhold retainage on stored materials and some do not, which is why the toggle above exists. Submitting stored materials without the backup is a common reason a first application comes back unpaid. For the full billing sequence, read the construction progress billing guide.
Frequently Asked Questions
- What is a schedule of values in construction?
- A schedule of values (SOV) breaks the total contract sum into individual line items, each assigned a dollar value, so progress can be billed against measurable components instead of the contract as a whole. It is submitted for approval at the start of the job and then becomes the billing baseline for every pay application. On AIA contracts the SOV lives on form G703, the continuation sheet that supports the G702 payment application. The sum of all line items must equal the contract sum exactly.
- What is the difference between AIA G702 and G703?
- G702 is the one-page Application and Certificate for Payment — the summary that shows the contract sum, total completed and stored to date, retainage, previous payments, and the current payment due, signed and notarized. G703 is the Continuation Sheet: the line-by-line schedule of values behind that summary, showing scheduled value, work completed this period and previously, materials presently stored, percentage complete, and balance to finish for each item. G702 is the cover; G703 is the detail that proves it.
- How do you calculate the current payment due on a pay application?
- Total the work completed to date across all line items, add materials presently stored on site, subtract retainage at the contract rate, then subtract everything already certified on previous applications. The remainder is the current payment due. The order matters: retainage is withheld from the cumulative earned amount, not from the current period's work alone, which is why a period with little progress can still produce a payment once retainage steps down.
- Is retainage withheld on stored materials?
- It depends on the contract, and it is worth checking before submitting. Many contracts withhold retainage on both installed work and stored materials, some exclude stored materials from retainage entirely, and some refuse stored materials in a pay application altogether unless they are on site, insured, and supported by paid invoices or bills of sale. Because the treatment varies, this calculator lets you apply retainage to stored materials or exclude them so you can model either structure.
- Why does front-loading a schedule of values cause problems?
- Front-loading means assigning inflated values to early line items such as mobilization or submittals so cash arrives sooner. Owners and their construction lenders look for it specifically, and the consequences are real: the SOV gets rejected and the whole first application is delayed, or it is approved and you spend the back half of the job performing work you have already been paid for, with no money left to finish. A defensible SOV that gets approved the first time usually beats an aggressive one that triggers a round of revisions.
- How detailed should a schedule of values be?
- Detailed enough that percentage complete is defensible, and no more. Too few lines and you end up arguing about whether a large lump item is 40% or 60% done, which is exactly the dispute that delays payment. Too many and every application becomes an accounting exercise and small errors multiply. Breaking the work along the way it is actually installed — by system, phase, floor, or area — gives you line items whose progress someone can walk out and verify, which is the real test.
- Can you change the schedule of values after it is approved?
- Generally only through a change order. The approved SOV is the billing baseline, so moving value between line items after approval usually requires the architect's or owner's consent and often looks like an attempt to accelerate cash. Approved change orders are the legitimate mechanism: they add new lines or adjust existing values, and the revised contract sum flows through to the next application. This is why change orders left unprocessed are so damaging — the work is done but there is no approved line to bill it against.
- What is the balance to finish on a G703?
- The balance to finish is the scheduled value of a line item minus everything completed and stored to date — the dollar value of work remaining on that line. It is the column owners and lenders read most closely, because comparing it against remaining time is the fastest way to spot a job that is billing faster than it is building. If your balance to finish is small while significant physical work remains, expect questions on the next application.
Quote, Finance, and Run Every Job in One Platform
See how SubcontractorHub carries an accepted proposal into the schedule of values, so progress billing, change orders, and retainage all run off the same job record instead of a spreadsheet somebody rebuilds every month.
Book a DemoResources
Related Guides & Tools
- Construction Progress Billing: AIA G702/G703
- Construction Retainage Explained
- Retainage Calculator
- Change Order Calculator
- WIP Schedule Calculator
- Accounts Receivable & DSO Calculator
- Construction Billing Software
- Mechanical Contractor Software
- How to Bid Construction Jobs
- Construction Project Management
- Embedded Contractor Financing
- More Free Contractor Tools
Pay application requirements are set by your contract and by the owner, architect, or lender reviewing it. AIA G702 and G703 are copyrighted forms published by the American Institute of Architects; this tool reproduces the arithmetic of a standard application and is not an AIA document, is not affiliated with or endorsed by the AIA, and is not a substitute for the official forms where your contract requires them. Retainage rules, stored-material conditions, and certification requirements vary by contract and by state. All calculations are estimates based on historical information and should be verified by the user. This tool is provided as a free service for planning purposes only and is not a substitute for professional accounting, financial, or legal advice.