//

Free Contractor Tool

Change Order Calculator

Price a change order the way it should be priced: direct cost, then overhead and profit on your own work, then a separate markup on subcontractor work — with a running check on how much of the original contract your changes now represent.

Built by SubcontractorHub — the software contractors use to quote, finance, and run every job.

Book a Demo
Contractor and client reviewing and signing a change order document

Price a Change Order

Enter the contract, the direct cost of the added scope, and the markup your contract allows. The breakdown below is the same structure most owners expect to see on a submitted change order.

1. The contract

$
$

Used for the cumulative percentage.

2. Direct cost of the change

$
$
$
$

3. Markup

%

Typically 5–10%.

%

Typically 5–10%.

%

Often capped at 5%.

Change order price

$18,074.00

Markup captured

$2,674.00

14.8% of the change order

New contract total

$268,074.00

This change is 7.2% of original

Own direct cost (labor + material + equipment)$11,900.00
Overhead @ 10%$1,190.00
Profit @ 10%$1,309.00
Subcontractor cost$3,500.00
Subcontractor markup @ 5%$175.00
Change order total$18,074.00

Cumulative change orders: 7.2% of the original contract — Approaching review territory

Many owner contracts and institutional specs require formal written approval once cumulative changes pass 10%. Make sure every one of these is signed, not just verbally agreed.

This calculator prices direct cost plus the markup percentages you enter. It does not price delay, disruption, lost productivity, extended general conditions, bond or insurance adjustments, or escalation, any of which may be recoverable and should be priced separately. Allowable markup on changes is governed by your contract, which may cap it below the figures used here. All calculations are estimates based on historical information and should be verified by the user. This tool is provided as a free service for planning purposes only and is not a substitute for professional accounting, financial, or legal advice.

From Material Takeoffs to a Signed Proposal

SubcontractorHub is the platform contractors use to turn takeoffs like these into a branded proposal, financing the customer can accept on the spot, and a scheduled job — without re-entering the job anywhere. This tool is free to use; the platform is here if you want a closer look.

Almost every unrecovered change order started as a conversation in a driveway. The pricing is the easy part — the hard part is that the crew proceeded on a verbal go-ahead and the paperwork caught up three weeks later, by which time nobody agrees on what was said. When the change gets captured against the job the day it happens, with photos and a cost breakdown attached, it becomes a signed document instead of an argument. That is what contractor management software is for, and it is why the proposal and quoting workflow matters as much on changes as it does on the original bid.

How Change Order Pricing Works

A change order has two cost streams that get marked up differently, and collapsing them into one number is the most common pricing error:

CO total = (own cost × (1 + overhead) × (1 + profit)) + (sub cost × (1 + sub markup))

Overhead and profit compound — profit is calculated on cost plus overhead, not on bare cost. Subcontractor work carries its own, usually lower, markup because the sub has already marked up its labor and materials.

Use the markup your contract allows, not the one that feels comfortable

The common range is 10% to 15% combined overhead and profit on own work, with many institutional and public contracts capping it at 10% and limiting subcontractor markup to 5%. Read the contract before you price. Where it specifies allowable markup, that number governs — and where it does not, your original bid markup is the right default. Discounting markup on changes to keep a relationship pleasant is a reliable way to deliver a profitable job at break-even, because the overhead those added hours consume does not discount itself.

Watch the cumulative percentage, not just the individual change

Each change can look reasonable on its own while the total quietly crosses a contractual threshold. Under roughly 5% of the original contract is routine. Past 10%, many owner agreements require formal written approval. Above 20% you can run into re-bid provisions, bonding review, or a cardinal change argument — the claim that the accumulated changes have altered the job so fundamentally that the original contract no longer describes it. Knowing where you sit before you submit the next one is worth more than optimizing its markup.

The cost you will forfeit is disruption

Added scope almost never arrives at a convenient moment. Crews come off planned work, sequences get rebuilt, and a two-day change pushes a milestone by a week. Many contracts permit recovery of those impacts, but only with records made at the time — daily logs, manpower counts, and schedule updates. Reconstructed documentation loses. Price the direct work with the calculator above, then price disruption separately and attach the evidence, because it is the line item owners challenge first and contractors support worst.

Never build on a verbal approval

A signed change order before work starts is the whole ballgame. If the owner issues a directive to proceed while price and time stay open, that is a different instrument — your cost records become the entire basis of recovery, so track them separately from base contract costs starting the first day. Document the scope, the requester, the itemized cost, the markup, and the schedule impact in calendar days, and attach photos and the RFI or drawing reference. The standard to hold yourself to is whether someone who never set foot on the job could read the file a year later and understand what changed, why, and what it cost.

Frequently Asked Questions

How do you calculate a construction change order?
Start with the direct costs the change actually adds: labor, materials, equipment, and any subcontractor work. Apply your overhead percentage and then your profit percentage to the work your own crews perform. Apply a separate, usually lower, markup to subcontractor work. Add the two together and that is the change order price. Expressed as a formula: change order total = (own direct costs × (1 + overhead) × (1 + profit)) + (subcontractor cost × (1 + sub markup)).
What is a typical markup on a change order?
The common industry range is 10% to 15% combined overhead and profit on the contractor's own work, with many institutional and public contracts capping it at 10%. Markup on subcontractor work is usually lower — often 5%, sometimes up to 10% — on the reasoning that the sub has already marked up its own labor and materials. The single most important rule: check your contract first. If it specifies allowable markup on changes, that number governs regardless of what is typical.
Should change orders use the same markup as the original bid?
As a default, yes — if the job was priced at a given markup, changes to that job should carry the same markup. Cutting your markup on changes to seem accommodating is one of the more reliable ways to finish a profitable job at break-even. There is an argument for a higher markup on changes, because out-of-sequence work is genuinely less efficient than planned work, but many contracts prohibit that. What you cannot do is absorb the overhead on added scope and expect the original margin to survive.
What percentage of a contract is a normal amount of change orders?
Cumulative change orders under about 5% of the original contract value are routine. Between 5% and 10% is common and usually manageable. Once cumulative changes pass 10%, many owner contracts require formal written approval, and above 20% you can run into re-bid clauses, bonding review, or a cardinal change argument. Tracking the cumulative percentage as you go — not just the value of each individual change — is what keeps you ahead of that conversation.
Can you charge for delay or disruption in a change order?
Often yes, but it has to be documented and it is the most frequently forfeited cost on any change. Added scope rarely arrives at a convenient moment: crews get pulled off planned work, resequencing costs productivity, and a two-day change can push a milestone by a week. Many contracts allow recovery of these impacts, but only with contemporaneous records — daily logs, manpower counts, and schedule updates made at the time, not reconstructed later. This calculator prices direct cost and markup; delay and disruption should be priced separately and supported by documentation.
Why do contractors lose money on change orders?
Three reasons dominate. First, work performed on a verbal go-ahead that never becomes a signed change order — the cost is real and the recovery is not. Second, markup discounted to keep the relationship comfortable, which quietly moves the whole job's margin down. Third, unpriced disruption: the direct labor hours get captured but the productivity loss on the surrounding work never does. All three are documentation problems more than pricing problems, which is why the fix is a process that captures the change at the moment it happens.
What is the difference between a change order and a change directive?
A change order is a negotiated, signed agreement on both scope and price before the work proceeds. A construction change directive — sometimes called a field order or a unilateral change — is the owner instructing you to proceed while price and time remain unsettled. Directives keep the job moving but shift risk onto the contractor, so if you are working under one, your cost records are the entire basis of your eventual recovery. Track those costs separately from base contract costs from day one.
How should change orders be documented?
At a minimum: a written description of the added or deleted scope, the reason for the change and who requested it, an itemized cost breakdown by labor, material, equipment and subcontractor, the markup applied, any schedule impact in calendar days, and signatures from both parties before work starts. Attach photographs and the relevant drawing or RFI reference. The test to apply is whether someone who was never on the job could read the file in a year and understand what changed, why, and what it cost.

Quote, Finance, and Run Every Job in One Platform

See how SubcontractorHub captures a change against the job the day it happens — scope, photos, cost breakdown, and signature — so the change order is a document instead of a disagreement.

Book a Demo

Change order pricing is governed by the terms of your contract, which may cap allowable overhead, profit, and subcontractor markup below the percentages entered here, and may impose notice deadlines that affect recovery. Figures produced by this tool cover direct cost and markup only and exclude delay, disruption, lost productivity, extended general conditions, bond, insurance, and escalation. All calculations are estimates based on historical information and should be verified by the user. This tool is provided as a free service for planning purposes only and is not a substitute for professional accounting, financial, or legal advice.